Design FMEA for Custom Battery Packs: What to Require from a Pack Supplier

A design FMEA for a custom battery pack is not a formality that arrives with the qualification report; it is the document that shows, line by line, how the pack design can fail to deliver each of its functions, what controls the design has against those failures, and which tests exist because of them. Buyers who treat the DFMEA as a supplier-internal template tend to receive a spreadsheet with generic rows copied from an automotive cell FMEA, no link to the actual pack architecture, and no answer when a field issue surfaces. The fix is to scope the DFMEA deliverable in the RFQ and design review with the same care as the test plan: a defined function list, an agreed scoring and priority method, and explicit links from every high-priority failure mode to a test, an inspection or a process control. This article describes what a usable pack-level DFMEA contains and how to review it.

Technician at a computer bench beside trays of cylindrical cells during pack verification
Illustrative image: verification work at a pack bench. Each bench test in a qualified program should trace to a failure mode identified in the design analysis.

What a pack DFMEA must cover that a generic one misses

The method itself is standardized. IEC 60812:2018 explains how failure modes and effects analysis, including the FMECA variant, is planned, performed, documented and maintained, and it applies to hardware, software and processes in any combination. The third edition also added alternative risk-priority calculations and a criticality-matrix method, which matters later in this article. A generic application of that method, however, will not automatically produce a good pack analysis. A battery pack has function groups that rarely appear in a buyer’s mechanical FMEA template: energy delivery under the specified load profile, protective functions that must act at defined thresholds, measurement and communication functions feeding those protections, and mechanical and thermal containment functions. Each group fails in its own way, and the analysis is only useful if every group appears with its own failure modes.

Two boundary lines keep the document honest. First, DFMEA versus PFMEA: the design analysis asks what the chosen architecture can fail to do, while the process analysis asks what the factory can build wrong. A supplier who answers a design question with a process row, for example listing welding parameter drift as the cause of a design-level connection failure, has hidden the design question of whether the interconnect concept has enough margin for that drift. Second, the DFMEA is a living document with defined update triggers, not a one-time attachment; every design change, every field finding and every test failure should either close a row or open a new one.

A structure you can review line by line

The fastest quality check on a supplier DFMEA is whether its rows describe this pack or any pack. The example rows below show the level of specificity that makes review possible; a supplier document should look like this, with the actual architecture, numbers and thresholds of your program filled in.

FunctionFailure modeEffect at pack and system levelPotential causeDesign controlDetection control
Deliver rated discharge current for the specified pulse durationInterconnect joint overheats under peak currentVoltage sag below load cut-off; local heating at the jointJoint resistance margin too small for pulse duration and ambientJoint resistance budget per joint; current density limits in the layoutJoint resistance measurement at pack test
Open the charge path at the cell overcharge thresholdProtection does not act at the specified thresholdCells exceed maximum voltage; safety function lostThreshold set outside the cell specification; single-channel protectionRedundant protection path; thresholds derived from the cell datasheetFault-injection test at pack level
Report cell voltages within the stated accuracyReported voltage drifts outside the error bandWrong balancing decisions; premature cut-off or late protectionSense-line design, calibration plan or input range mismatchError budget across temperature; calibration points definedReference-meter comparison at outgoing test
Contain a single-cell thermal eventPropagation to adjacent cellsPack-level fire risk; system damageInsufficient thermal barriers or venting pathPropagation analysis and barrier designPropagation type-test at module or pack level
Withstand the specified vibration profileFastener loosens; sense line fracturesIntermittent faults in serviceResonance overlap with the mounting geometryModal check against the profile; fastener locking methodVibration test with functional monitoring
Preserve isolation between live parts and enclosureCreepage or clearance below the required distanceInsulation fault risk at high voltageLayout change during toolingIsolation scheme with stated distancesDimensional audit plus dielectric test

A document that looks like this can be reviewed in a working session. A document whose function column contains only supply power and protect cells cannot, because no test plan or audit finding can attach to a row that vague.

Scoring and prioritization without false precision

Most supplier FMEA spreadsheets still carry a single risk priority number, severity times occurrence times detection, multiplied out to three digits. The number invites ranking that the underlying scales cannot support: two modes rated 200 can carry entirely different risks, and a 192 against a 200 says nothing reproducible. IEC 60812:2018 added alternative calculation methods and a criticality-matrix approach for exactly this reason, and automotive-aligned practice has moved to action-priority logic in which the classes of severity, occurrence and detection, not their product, decide what must happen next. The AIAG core tools page documents that framework for buyers working to automotive-derived quality agreements.

What the buyer should require is not a particular scale but a stated one. The table below is the minimum rule set to fix before the design review, so that the supplier’s prioritization is reproducible and every high-priority row is dispositioned.

RuleWhat to requireWhy it matters to the buyer
Severity anchorsWritten definitions per level, referenced to system consequences: loss of protective function, loss of availability, degradation, cosmeticPrevents the supplier from scoring severity against pack-internal effects only
Occurrence basisEach rating justified by data: field history, comparable designs, or an explicit assumption stated as suchOccurrence guesses drive attention; unfounded ones misdirect it
Detection definitionNamed control per row: which test, when in the flow, what sample sizeA high detection score must correspond to a test that actually exists in the plan
Priority ruleClass combination decides the action: mandatory redesign, mandatory verification, or document-and-monitorReplaces the single magic number; every red row has an owner and a due action
Closure evidenceEach open action links to a change record, a test report or a control plan entryConverts the FMEA from a spreadsheet into a traceable risk decision record

Linking the DFMEA to tests, audits and field data

A pack DFMEA earns its place in the program through three connections. The first is to the verification plan: every failure mode rated high on severity or priority must map to a test that would catch it, at the level where the failure lives. Where the design analysis cannot produce a test, complementary analysis methods fill the gap; fault tree analysis under IEC 61025:2006 is the usual companion for protective-function logic, because it works top-down from the system-level event while the FMEA works bottom-up from components. The Canadian NRC hydrogen and energy storage standards library maintains a useful reference list pairing these methods in its system safety analysis section.

The second connection is to the factory. Process-side controls that keep the design intent alive belong in the PFMEA and the control plan, and the buyer verifies them in a station-by-station walk-through, as set out in the supplier process audit checklist. The two documents must reference each other: a design row whose cause is manufacturability should appear as a process row with a control, and a process row whose failure escapes the factory should feed back into the design analysis. Peer-reviewed work on lithium-ion battery assembly risk shows this linkage in practice; a risk analysis method for potential failure modes in the battery assembly process demonstrates how process failure modes are identified, weighted and tied to corrective actions in a real assembly context.

The third connection is to incoming and field evidence. Incoming inspection under the pack incoming inspection plan and joint-level verification such as the tab welding acceptance evidence are the first points where a design assumption meets produced hardware. When a pack does come back from the field, the root-cause workflow in the field failure analysis guide should end by updating the DFMEA: a mode the analysis missed is a design-scope gap, and a mode the analysis predicted but failed to prevent is a control gap. Both outcomes change the document, and the next revision of the pack should show it.

What to require in the RFQ and design review

The deliverable is definable in a page. The checklist below is what we recommend attaching to the RFQ alongside the test plan, and reviewing at the design freeze gate; it complements the engineering inputs in the custom pack RFQ checklist rather than duplicating them.

Deliverable itemRequirement to stateReview evidence
Function listPack functions decomposed to the level of the interface specification, including protective, measurement and communication functionsFunction list agreed line by line at the kick-off review
Scope boundaryDFMEA covers the pack design; PFMEA and control plan cover the process; cross-references statedBoundary table in the document header
Scoring methodNamed scale with written anchors and an action-priority or criticality-matrix ruleRule set accepted before scoring begins
Update triggersDesign change, test failure, field return, supplier change: each reopens affected rowsRevision history with dated changes and reasons
DispositionEvery high-priority row carries an owner, an action and closure evidence, or a documented decision to acceptOpen-items list with zero unassigned rows at design freeze
TeamAnalysis performed by a cross-functional team including the design owner and the process owner, not by one authorParticipant list per revision

Scoped this way, the DFMEA becomes the connective tissue between what the pack was designed to do, what the tests prove, and what the factory and the field observe. It also gives both parties a shared language when something changes: a modification is not just a drawing update, it is an event that reopens named rows, and the risk decision is recorded where both sides can see it.